ConstructSim Planner CONNECT Edition Update 5 Help

To View the Tasks During Animation Preview

  1. In the Animation Producer dialog, select the schedule you want to preview.
  2. Select the Animation Preview tool ().

    The Animator Preview window opens.

  3. Click the Display Active Tasks During Preview tool ( Visualization > Animate > Schedule Simulation ).

    The Active Schedule Entries dialog opens.

  4. In the Animator Preview window, click the Start button.

    As the animation plays, the Active Schedule Entries dialog shows the tasks, the start and end times and percentage complete.